December 9, 2008

 

  • The project is on schedule for substantial completion in April 2009.

  • The steel erector is completing the welding of the roof decking for both City Hall and Library.

  • The exterior wall studs are being installed on both City Hall and Library.

  • The HVAC duct work and the electrical conduits are being installed on both the City Hall and Library.

  • Staff still in discussions with the architect and electrical engineer regarding the installation of a transfer switch for an emergency generator.

  • West side parking and driveways have been poured.

  • Brick scheduled to begin this week.

  • Roof panels scheduled to begin this week.

  • City staff is meeting with different vendors for telephone systems.

  • City Administrator working on quotes for signage.

 

 


 